66-1289. Wind turbine lighting requirements; inclusion of light-mitigating technology systems; implementation timeline; notice of progress of installation of system; responsibility of costs. (a) On and after July 1, 2023, no new wind energy conversion system shall commence commercial operations in this state unless the developer, owner or operator of the wind energy conversion system applies to the federal aviation administration for installation of a light-mitigating technology system that complies with federal aviation administration regulations 14 C.F.R. § 1.1 et seq. If approved by the federal aviation administration, the developer, owner or operator of such wind energy conversion system shall install the light-mitigating technology system on approved turbines within 24 months after receipt of such approval.

(b) (1) On and after January 1, 2026, any developer, owner or operator of a wind energy conversion system that has commenced commercial operations in the state without a light-mitigating technology system shall apply to the federal aviation administration for installation and operation of a light-mitigating technology system that complies with federal aviation administration regulations 14 C.F.R. § 1.1 et seq. within six months after the execution of a new power offtake agreement related to such wind energy conversion system. If approved by the federal aviation administration, the developer, owner or operator of such wind energy conversion system shall install the light-mitigating technology system on approved turbines within 24 months following such approval.

(2) Any county may issue revenue bonds pursuant to K.S.A. 12-1741b, and amendments thereto, for the purpose of paying all or part of the costs of the purchase, acquisition and equipping of a light-mitigating technology system, subject to the approval of the federal aviation administration, for a wind energy conversion system that has commenced commercial operations in the state without a light-mitigating technology system.

(c) Any vendor that is selected for installation of a light-mitigating technology system on a wind energy conversion system pursuant to the requirements of this section and is approved by the federal aviation administration for such installation shall provide to the Kansas department of transportation aviation division, in the form and manner prescribed by the division, notice of the progress of the installation of such light-mitigating technology system. If the installation of the light-mitigating technology system is delayed beyond the 24-month installation requirement established pursuant to this section, such vendor shall provide notice to the Kansas department of transportation aviation division not less than once every three months to provide an update on the reasons for the delay and the current status of the installation. The division may establish policies and procedures to establish a uniform schedule for submitting notice pursuant to this subsection.

(d) Any costs associated with the installation, implementation, operation and maintenance of a light-mitigating technology system shall be the responsibility of the developer, owner or operator of the wind energy conversion system.

(e) As used in this section:

(1) "Light-mitigating technology system" means aircraft detection lighting or any other comparable system capable of reducing the impact of facility obstruction lighting while maintaining conspicuity sufficient to assist aircraft in identifying and avoiding collision with a wind energy conversion system.

(2) "Power offtake agreement" means a long-term contract that provides for:

(A) The provision of the whole or any part of the available capacity or the sale or other disposal of the whole or any part of the output of a wind energy conversion system; or

(B) a contract for differences or financial hedge tied to the output from the wind energy conversion system.

(3) "Wind energy conversion system" means an electric generation facility consisting of five or more wind turbines that are 50 feet or taller in height and any accessory structures and buildings, including substations, meteorological towers, electrical infrastructure, transmission lines and other appurtenant structures.

History: L. 2023, ch. 20, § 1; April 20, 2023.


 | Next


LEGISLATIVE COORDINATING COUNCIL
  12/02/2024 Meeting Notice
  11/14/2024 Meeting Notice Agenda
  10/23/2024 Meeting Notice Agenda
  09/09/2024 Meeting Notice Agenda
  08/21/2024 Meeting Notice Agenda

  LCC Policies

REVISOR OF STATUTES
  Chapter 72 Statute Transfer List
  Kansas School Equity & Enhancement Act
  Gannon v. State
  A Summary of Special Sessions in Kansas
  Bill Brief for Senate Bill No. 1
  Bill Brief for House Bill No. 2001
  2024 New, Amended & Repealed Statutes By Bill
  2024 New, Amended & Repealed Statutes By KSA
  2023 New, Amended & Repealed Statutes By Bill
  2023 New, Amended & Repealed Statutes By KSA
USEFUL LINKS
Session Laws

OTHER LEGISLATIVE SITES
Kansas Legislature
Administrative Services
Division of Post Audit
Research Department